PROJECT IMPLEMENTATION STATUS

  • Thawhkhatna(Project-I): ah chuan veng hrang hranga mi thir tuizem (Zonal Tank) tuiek chhe tawh pasarih (7Nos) chu RCC tuizem thar siam a ni a, Chowkidar qtr/Site office-paruk(6Nos) te, Tuitihthianghlimna(Chlorinator) hmunhnihah bun a ni a,Tui-metre consumer 15000 tan leia vuah fel a ni tawh bawk.Heng tuizemte leh thildangte hi PHE Department hnena hlanfel a ni tawh.

Project-1hnuaia Water Supply sub-project: 

  • 7 nos. of Pressed Steel Tanks (PST) hmantlaktawhlohchu RCC a thlak a ni a, Chungtechu:-

Seventhday Tlang Reservoir (1746 KL) , Zemabawk TB Tlang (600 KL), Bawngkawn (423 KL), Mission Vengthlang (370 KL), Govt. Complex (212 KL), Armed Veng (405 KL) lehTlangnuam (490 KL) Zonal tank te an ni. HeibakahhianSevice Buildings-site office leh quarters (for operations) te sak a ni bawk.

Contractor M/s S.S Construction, Chaltlang JV with H. Sanga, Chanmari
Contract AmountINR 432.00 lakhs
ExpenditureINR 541.10 lakhs
Date of Commencement24th April, 2010
Date of Completion2nd April, 2012
Up to Date progress (As on Oct., 2016)Commissioned  and handed over to PHED

 

  • Tuitihthianghlimna Chlorinator (1000 MAC leh 500 MAC) hmun hnih (Tuikhuahtlang Main Reservoir leh Booster Pump, Chanmari)-ah bun fel tawh a.
Contractor M/s De Nora India Limited,  Plot Nos. 184,185 & 189 Kundaim Industrial Estate,  Kundaim-403115 Goa, India.
Contract AmountINR 41.65 lakhs
ExpenditureINR 41.65 lakhs
Date of Commencement24th March, 2010
Date of Completion26.11.2010
Up to Date progress (As on Oct., 2016)Commissioned  and handed over to PHED

 

  • Tui meter 15,000 vuahzawhtawh a ni. 
Contractor M/s Aman Engineering Works,   C 54-55, Focal Point Extension, Jalandar-144004,Punjab, India
Contract AmountINR 324.83 lakhs
ExpenditureINR 324.83 lakhs
Date of Commencement25th June, 2010
Date of Completion30th March, 2012
Up to Date progress (As on Oct, 2016)Commissioned  and handed over to PHED

 

Heng Contract hnate hi ADB Procurement Guidelines ang a Tender chhuah a, a chhang hniam be rthlan thin anni.

  • Thawhhnihna(Project-II): ah chuanTuisemchhuahna pipeline siam that hna Zone pariat(8) ah thawhmek a ni a, ZunlehekthliluankhawmnaSewarage Network, Aizawl chhuah lam veng 22 huamturleh  a thlitfimna  Sewage Treatment Plant chuthawhmek a nibawk. Tin Aizawl hmunlunlaiah Community Toilet sawm (10Nos), Septic Tank tihfaina (Cess Pool Cleaner) turpanga (5-Nos),Booster Pump Chanmari &Tlangnuam ah te,Zonal Tank pathum(3-Nos) Tanhril,Mualpui,Hlimen ah tethawhtawhanibawk. Zonal Tank a tuilutlehchhuaktehnaTuimetrelian (BulkMetre) 85Nos, Tui-metre consumer -20000 tan te, LuangmualatangaDihmunzawl PHE tui pump hmunatan a power supply peknatur a huamtel bawk.
  • Water Supply Sub-Project:
  • Water Supply distribution networks: Greater Aizawl Water Supply Scheme Phase-I leh Phase-II chhunga 8-Zone a mi design that a pipe tihlenleh pipe line extension te a huam a. Tui pipe 112.15 km a thui, size hranghrang (32mm-350 mm dia) siamthatnaatannatur a ni. Main Reservoir atanga Zonal Tank hmunhranghrang a tuipekchhawnna pipe feeding mains (14.00 km) tihlente, Zonal Tank atangaDistribution Systemsiam that teleh extension pipe (98.16 km) te a huam a ni.

Distribution Networks te chu: 

Location                           Pipe length(KM)                                Progress

Govt. Complex                             5.69                                         100%

SeventhdayTlang                          15.84                                       97.00%

Luangmual                                    14.79                                       89.24 %

Mission Veng                                7.26                                         32.37%

Bawngkawn                                  11.34                                       37.7 %

Laipuitlang                                    22.14                                       4.4 %

Zemabawk 1                                 12.69                                       98.58 %

Zemabawk  2                                11.40                                       98.50 %

Feeding mains:

Tuikhuahtlang to                           6.25                                         99.40%

7thday tlang,

Luangmual etc

Durtlang TV Centre to

Sihphir 1&2                                   6.71                                         85.39 %

 Grand Total length:                   107.55 kM

ContractorM/s Tantia Construction Ltd.,  Kolkata
Contract AmountINR 4338lakhs
Expenditure
INR 4306 lakhs
Date of Commencement29th August, 2013
Date of CompletionApril, 2016 extension granted upto December, 2017
Up to Date progress (As on Oct., 2016)68.37 %80.23 Km laid out of 107.55 Km

TunahhianDurtlang to Sihphirtuipeknatur line te, TuikhuahtlangatangaSeventhdaytlanglehLuangmualtepeknaturte, Zemabawk AL Road ah te,Bawngkawn ah te,SeventhdaytlanglehLaipuitlangReservoir in a chawm area te, Mission Vengtethawhmek an ni a. 

  • Zonal Tank tharpathum(3): Mualpui (750 KL), Tanhril (450 KL) leh S. Hlimen (350 KL) Zonal Tank.
ContractorM/s S.S Construction, Chaltlang
Contract AmountINR 285.99 lakhs
ExpenditureINR 282.00 lakhs
Date of Commencement25th June, 2012
Date of CompletionJanuary,2014
Up to Date progress (As on Oct., 2017)Commissioned  and handed over to PHED

Flow meter( 85) leh water meter (20,000): 19,286 water meter leh flow metre 39 vuahzawhtawh a ni. 

ContractorM/s Aman Engineering Works,   C 54-55, Focal Point Extension, Jalandar144004,Punjab, India
Contract AmountINR 638.82 lakhs
ExpenditureINR 629.00 lakhs
Date of Commencement21st September, 2012
Date of CompletionApril, 2016
Up to Date progress (As on Oct., 2016)Domestic meter – 20,000 installed


Flow meter  – 55 nos. Installed

Chanmari Booster lehTlangnuam Booster Pumping Station– Completed.

ContractorM/s Johnson Diesel Sales & Services
Contract AmountINR 54 lakhs
ExpenditureINR 53.95 lakhs
Date of Commencement16th May, 2012
Date of Completion31st August, 2013
Up to Date progress (As on Oct., 2017)Commissioned  and handed over to PHED
  • Dedicated Power Supply: 132 KV Power transmission line leh Power sub-station (Dihmunzawl) a ni.
ContractorM/s EMC Ltd,Kolkata
Contract AmountINR 1641.63lakhs
ExpenditureINR 1181.00 lakhs
Date of Commencement27th November, 2013
Date of CompletionNovember, 2016 (Extended upto Nov, 2017)
Up to Date progress (As on Oct., 2017)43.00%

Sewerage & Sanitation Sub-Project:

Sewerage & Sanitation Sub-Project hnuaiahhianheng contract hnate hi implement mek a ni:-

  • Construction of 10 Community Toilet Blocks

Bethlehem Vengthlang, Bawngkawn Market, Zarkawtleh Mission Vengte, AMC (Thuampui Veng), College Veng, Kulikawn (Ngaizel) New Market, Zemabawk Bazar lehDawrpuiVengte an ni. Zawhfeltawhleh a enkawltutehnenahlanfelvekannitawh.

ContractorM/s Gangwal Engineering and Construction Ltd,Silchar
Contract AmountINR  179 lakhs
ExpenditureINR 178.81 lakhs
Date of Commencement29th August, 2013
Date of CompletionAugust,2015, (Extended upto Oct, 2015)
Up to Date progress (As on Oct., 2017)Completed and handed over

Approach Road and Land Development for STP

ContractorM/s CLT ConstructionLtd,Kolkata
Contract AmountINR 343lakhs
ExpenditureINR 343lakhs
Date of Commencement26th  February, 2013
Date of CompletionNovember, 2016 (Extended upto Dec., 2016)
Up to Date progress (As on Oct., 2017)100% Completed

Supply, Installation & Commissioning of 5 Cess Pool Cleaners

ContractorM/s Gangwal Engineering and Construction Ltd,Silchar
Contract AmountINR 87.57 lakhs
ExpenditureINR 87.57 lakhs
Date of Commencement18th May, 2012
Date of CompletionOctober, 2013
Up to Date progress (As on Oct., 2017)Commissioned and handed over to AMC

Construction of Sewerage Treatment Plant

ContractorM/s Eco-Protection Engineers  Pvt Ltd,Chennai
Contract AmountINR 2246.27 lakhs
ExpenditureINR 1652 lakhs
Date of Commencement27th November, 2013
Date of CompletionNovember, 2016 (Extended uptoDecember., 2017)
Up to Date progress (As on Oct., 2017)81.2%

Providing, Laying, Jointing & Commissioning of Sewerage Networks (46 kms).

ContractorM/s Tantia Construction Pvt Ltd., Kolkatas
Contract AmountINR 3172.92 lakhs
ExpenditureINR 2169 lakhs
Date of Commencement27th November, 2013
Date of CompletionDecember, 2017
Up to Date progress (As on Oct., 2017)59.50%


Sewer line 18.19Km out of 46Km already laid and 768 Manhole constructed out of 2222 Nos.

 Procurement of Dustbins for Aizawl City

ContractorM/s Nilkamal Ltd Kolkata.
Contract AmountINR 343lakhs
ExpenditureINR 305lakhs
Date of Commencement16th June, 2015
Date of CompletionApril,2017 (Extended due to additional procurement)
Up to Date progress (As on Oct., 2017)100 %Completed
  • Thawhthumna(Project-III) ah hian Aizawl khawpuitana a tui pump belhna37-MLD capacity tan te, Tuipipehluitawhthuamthatnaturatanveng/zone dang 35-ah tepipesize chi hranghrangkm 255.88 Kmphum tum ani a, Tuidahkhawlnatuizem(Reservoir) thar9Nos , Ruahtuidahkhawlnatuizem(RWH) 10-Nos,Aizawl khawpuibawlhlawhlakkhawm a sawngbawlnahmun Sanitary Landfilte, Septik tank chhuaktharenchhinnaDemonstration of Septage management throuthBio-DigesterNos i.e Household 5150 (appx)atante atelbawkani. HenghnathawhnaturhianRs776.81Croreruahmanphawta ni a, ADB/ MoUDchuan a pawmfeltawhani.Tunahhianngawrhtak a thawhchhohmekania ,Kum 2019 ah chuanzawhfelhmanturahmalakmek a ni.

  • Water Supply Sub-Project:
  • Tui Supply 37 MLD Capacity a AugmentationKum2018 (Program completion time) water demand hi tuna tui supply capacity hiana chawmzotawh dawn lohavangin Intermediate (2030) demand 71.22 MLD meet theiturtal a program kalpui a ngaihavangin Project-3 ah hi chuan a tir project scope ruahmanbakah, Aizawl khawpuitana37MLD Tui pump belhnahna  hi a tela.
ContractorM/s Eco Protection Engineers Pvt Ltd,Chennai
Contract AmountINR 15667 lakhs
Expenditure
INR 1531 Lakhs
Date of Commencement30th March, 2017
Date of Completion42 –Months/ 30th of September 2020
Up to Date progress (As on Oct., 2017)Work execution Just Started with approval of drawings and start of procurement of materials by the contractor.

Contractor thlantak Eco Protection Engineers Pvt Ltd,Chennaitechuanhna an tan tawh a. Survey tezawh a nitawh a, Drawing leh Design teenfelmek a ni a, kawnglaihhna an tan tawh a tin hmanruate contractor in an la khawmmek a ni.

  • Water Supply distribution networks and feeding main :
ContractorM/s Vishwa-Gayatri (JV), Hyderabad
Contract AmountINR 14342.22 lakhs
Expenditure
2475 Lakhs
Date of Commencement9th May, 2016
Date of Completion48–Month/ 8th of May 2020
Up to Date progress (As on Oct., 2017)19.47 % Work execution Started only recently.


39 Km Length laid

Pipe phum tur zawng zawng hi  avaiin Km 255.88 ani a. Hetahhian Feeder main Tuizemlian a tuichhunluhnatur 33.66Km lehTuisemnatur 224.22 Km a tel a. Pipe size hi 40-400mm thleng a tel a ni a.A hna hi 24th November 2016 atanginanthawk tan tawh a ni.Khawchhunghmunengngemawzat ah hnathawhmek a ni a. Pipe lehhmanruamamawhtepoh order tawh a ni.

(iii) Zonal Tank Pakua(9): Sihphir – I (260KL), Sihphir – II (260 KL), ATC Durtlang (400 KL), RamhlunPWD Mual (260 KL), Lawipu (400 KL), Central Jail (400 KL), Tuiovamit (260 KL), Sakawrtuichhun (300 KL), Phunchawng (260 KL)

Rain Water Harvesting Tank sawm (10) : Sihphir (100 KL), Chaltlang Higher Secondary School (50 KL), Hrangchhuana High School (150 KL), Thuampui (100 KL), Bethlehem (100 KL), Bethlehem Vengthlang (100 KL), College Veng (100 KL), Tlangnuam (100 KL), Melthum (100 KL), Rangvamual (100 KL).

ContractorM/s S.S. Construction Chaltlang
Contract AmountINR 1200.55 lakhs
Expenditure
INR 533.00 lakhs
Date of Commencement9thMay, 2016
Tentative Date of Completion8thNovember, 2018
Up to Date progress (As on Oct., 2017)59.21 %

SCADA management System: Pumping System tharte, Tuisemdarhnalehtuidahkhawlzatte, Pipeline pressure zatte, Current hmandante, mumal taka hriatzungzunganihtheihnaturin control room pakhatatangin computer nen a thlunzawmtir tum ani. Tender chhuahtur a hmalakmek a ni.

  • Sanitation/Septage Management Sub-Project:
  • Construction of Bio-Digester

Defence technology-Bio-digester hi Septic Tank tha chi, khatvetheiloleh Soak Pit hranpasiamngailo a ni a, tuiril/effluentlo luangchhuak hi a rimchheve lo a,kawr a luantirmaitheihkhawp a him a ni. BioDigesterstehi chhungkaw 10, 20, 30 leh 50tetanahmantursiammek a nia.Hei hi technology innovationatanMoUD, GoI in a ruahmantel a ni. Hengbakahhian awareness and documentation tepawh a telbawk a ni.

Bio-Digester hna hi Contractor thlantak  M/s Superflow Engineering Corporation Pvt. Ltd. Gwalior tehianchaktakinhmaan la mek a,zone paruk a site 55 ah Bio- Digester hi siammek a ni.

ContractorM/s Superflow Engineering Corporation Pvt. Ltd. Gwalior
Contract AmountINR 1308 lakhs
Expenditure
INR 64 lakhs
Date of Commencement5thApril, 2017
Tentative Date of Completion30 Months/ 5thOctober, 2019
Up to Date progress (As on Apr. 18)22.86 %

(ii)Packaged Aerate Wastewater Treatment Plant – Johkasou

Packaged Aerate Wastewater Treatment Plant – Johkasou hiJapan technology hmangami 30, 100leh 500 tethlisawngbawlnaatan a hmantheihturabuatsaih tum a  ni.Hei hi Tender chhuah a la ni lo.

 

(iii) Single Window System

Tin, awlsam taka septage management kalpuianihtheihnaturin Single Window System hi AMC tenenatangkawp in mipui tan a chhawpchhuah tum anibawk.

Hei hi Tender chhuah a la ni lo.

 

 

  • Municipal Solid Waste Resource Management System Sub Project:
  • Construction of Sanitary Landfil& Compost Plant

Solid Waste Resource Management hnuaiahhianTuirialahBawlhhlawhsawngbawlnahmuntur SanitaryLandfilbuatsaihmekania a hetahhianhnathawhtur item techu:

 

  • 2 units of 11 TPD capacity Vermi-Compost Plant (wet waste) eachbawlhlawhtawihtheiatangachangpatleithasiamnatur.
  • 2 units of 37 TPD capacity resource management centre (dry waste)bawlhlawhtawitheiloatangahralhchhuahtheihturtangkaithliarhrannahmun.
  • 1 unit of 50 TPD mechanical composting planteachbawlhlawhtawihtheiatangakhawlhmangaleithasiamnatur.
  • Closure of existing dumping site,kanbawlhlawhpaihnahmanlaimektihtawp.

 

 

ContractorM/s V. Lalbiakzama, Venghlui
Contract AmountINR 3058 lakhs
Expenditure
INR  911 lakhs
Date of Commencement18thAugust, 2016
Date of Completion30 months/17th Feb 2019
Up to Date progress (As on Oct., 2016)12.52 %  Completed Work in full swing

 

(ii)  Procurement of 54 nos of Garbage Vehicles

Bawlhlawhpaihna Motor (Garbage Vehicle) 54 Noslei a ni a, AMC tehmanturinhlanfel a nitawhbawk.

 

ContractorM/s ZothanAutoworks-TPS Infra JV Aizawl
Contract AmountINR 985 lakhs
Expenditure
INR  1070lakhs
Date of Commencement31st Jan, 2017
Date of Completion18 months/31st July 2018
Up to Date progress (As on Oct., 2016)100%  Completed and handed over to user AMC

 

(iii)  Procurement of Wheel Barrow by Shopping

KhawlaibawlhlawhphiahfainaatanabawlhlawhphurhnaturWheel Barrowpawh lei tawhani.

Amount  INR 14.00 Lakhs

(iv)  Procurement of Protection material by Shopping

Bawlhlawhsawngbawltutehriselnangaihtuahin an hmanturkawr, Boot,Glove etc., (Personal protection equipments) teleifeltawhani.

Amount INR 10.00 Lakhs