PROJECT IMPLEMENTATION STATUS
- Thawhkhatna(Project-I): ah chuan veng hrang hranga mi thir tuizem (Zonal Tank) tuiek chhe tawh pasarih (7Nos) chu RCC tuizem thar siam a ni a, Chowkidar qtr/Site office-paruk(6Nos) te, Tuitihthianghlimna(Chlorinator) hmunhnihah bun a ni a,Tui-metre consumer 15000 tan leia vuah fel a ni tawh bawk.Heng tuizemte leh thildangte hi PHE Department hnena hlanfel a ni tawh.
Project-1hnuaia Water Supply sub-project:
- 7 nos. of Pressed Steel Tanks (PST) hmantlaktawhlohchu RCC a thlak a ni a, Chungtechu:-
Seventhday Tlang Reservoir (1746 KL) , Zemabawk TB Tlang (600 KL), Bawngkawn (423 KL), Mission Vengthlang (370 KL), Govt. Complex (212 KL), Armed Veng (405 KL) lehTlangnuam (490 KL) Zonal tank te an ni. HeibakahhianSevice Buildings-site office leh quarters (for operations) te sak a ni bawk.
Contractor | – | M/s S.S Construction, Chaltlang JV with H. Sanga, Chanmari |
Contract Amount | – | INR 432.00 lakhs |
Expenditure | – | INR 541.10 lakhs |
Date of Commencement | – | 24th April, 2010 |
Date of Completion | – | 2nd April, 2012 |
Up to Date progress (As on Oct., 2016) | – | Commissioned and handed over to PHED |
- Tuitihthianghlimna Chlorinator (1000 MAC leh 500 MAC) hmun hnih (Tuikhuahtlang Main Reservoir leh Booster Pump, Chanmari)-ah bun fel tawh a.
Contractor | – | M/s De Nora India Limited, Plot Nos. 184,185 & 189 Kundaim Industrial Estate, Kundaim-403115 Goa, India. |
Contract Amount | – | INR 41.65 lakhs |
Expenditure | – | INR 41.65 lakhs |
Date of Commencement | – | 24th March, 2010 |
Date of Completion | – | 26.11.2010 |
Up to Date progress (As on Oct., 2016) | – | Commissioned and handed over to PHED |
- Tui meter 15,000 vuahzawhtawh a ni.
Contractor | – | M/s Aman Engineering Works, C 54-55, Focal Point Extension, Jalandar-144004,Punjab, India |
Contract Amount | – | INR 324.83 lakhs |
Expenditure | – | INR 324.83 lakhs |
Date of Commencement | – | 25th June, 2010 |
Date of Completion | – | 30th March, 2012 |
Up to Date progress (As on Oct, 2016) | – | Commissioned and handed over to PHED |
Heng Contract hnate hi ADB Procurement Guidelines ang a Tender chhuah a, a chhang hniam be rthlan thin anni.
- Thawhhnihna(Project-II): ah chuanTuisemchhuahna pipeline siam that hna Zone pariat(8) ah thawhmek a ni a, ZunlehekthliluankhawmnaSewarage Network, Aizawl chhuah lam veng 22 huamturleh a thlitfimna Sewage Treatment Plant chuthawhmek a nibawk. Tin Aizawl hmunlunlaiah Community Toilet sawm (10Nos), Septic Tank tihfaina (Cess Pool Cleaner) turpanga (5-Nos),Booster Pump Chanmari &Tlangnuam ah te,Zonal Tank pathum(3-Nos) Tanhril,Mualpui,Hlimen ah tethawhtawhanibawk. Zonal Tank a tuilutlehchhuaktehnaTuimetrelian (BulkMetre) 85Nos, Tui-metre consumer -20000 tan te, LuangmualatangaDihmunzawl PHE tui pump hmunatan a power supply peknatur a huamtel bawk.
- Water Supply Sub-Project:
- Water Supply distribution networks: Greater Aizawl Water Supply Scheme Phase-I leh Phase-II chhunga 8-Zone a mi design that a pipe tihlenleh pipe line extension te a huam a. Tui pipe 112.15 km a thui, size hranghrang (32mm-350 mm dia) siamthatnaatannatur a ni. Main Reservoir atanga Zonal Tank hmunhranghrang a tuipekchhawnna pipe feeding mains (14.00 km) tihlente, Zonal Tank atangaDistribution Systemsiam that teleh extension pipe (98.16 km) te a huam a ni.
Distribution Networks te chu:
Location Pipe length(KM) Progress
Govt. Complex 5.69 100%
SeventhdayTlang 15.84 97.00%
Luangmual 14.79 89.24 %
Mission Veng 7.26 32.37%
Bawngkawn 11.34 37.7 %
Laipuitlang 22.14 4.4 %
Zemabawk 1 12.69 98.58 %
Zemabawk 2 11.40 98.50 %
Feeding mains:
Tuikhuahtlang to 6.25 99.40%
7thday tlang,
Luangmual etc
Durtlang TV Centre to
Sihphir 1&2 6.71 85.39 %
Grand Total length: 107.55 kM
Contractor | – | M/s Tantia Construction Ltd., Kolkata |
Contract Amount | – | INR 4338lakhs |
Expenditure | INR 4306 lakhs | |
Date of Commencement | – | 29th August, 2013 |
Date of Completion | – | April, 2016 extension granted upto December, 2017 |
Up to Date progress (As on Oct., 2016) | – | 68.37 %80.23 Km laid out of 107.55 Km |
TunahhianDurtlang to Sihphirtuipeknatur line te, TuikhuahtlangatangaSeventhdaytlanglehLuangmualtepeknaturte, Zemabawk AL Road ah te,Bawngkawn ah te,SeventhdaytlanglehLaipuitlangReservoir in a chawm area te, Mission Vengtethawhmek an ni a.
- Zonal Tank tharpathum(3): Mualpui (750 KL), Tanhril (450 KL) leh S. Hlimen (350 KL) Zonal Tank.
Contractor | – | M/s S.S Construction, Chaltlang |
Contract Amount | – | INR 285.99 lakhs |
Expenditure | – | INR 282.00 lakhs |
Date of Commencement | – | 25th June, 2012 |
Date of Completion | – | January,2014 |
Up to Date progress (As on Oct., 2017) | – | Commissioned and handed over to PHED |
Flow meter( 85) leh water meter (20,000): 19,286 water meter leh flow metre 39 vuahzawhtawh a ni.
Contractor | – | M/s Aman Engineering Works, C 54-55, Focal Point Extension, Jalandar144004,Punjab, India |
Contract Amount | – | INR 638.82 lakhs |
Expenditure | – | INR 629.00 lakhs |
Date of Commencement | – | 21st September, 2012 |
Date of Completion | – | April, 2016 |
Up to Date progress (As on Oct., 2016) | – | Domestic meter – 20,000 installed Flow meter – 55 nos. Installed |
Chanmari Booster lehTlangnuam Booster Pumping Station– Completed.
Contractor | – | M/s Johnson Diesel Sales & Services |
Contract Amount | – | INR 54 lakhs |
Expenditure | – | INR 53.95 lakhs |
Date of Commencement | – | 16th May, 2012 |
Date of Completion | – | 31st August, 2013 |
Up to Date progress (As on Oct., 2017) | – | Commissioned and handed over to PHED |
- Dedicated Power Supply: 132 KV Power transmission line leh Power sub-station (Dihmunzawl) a ni.
Contractor | – | M/s EMC Ltd,Kolkata |
Contract Amount | – | INR 1641.63lakhs |
Expenditure | – | INR 1181.00 lakhs |
Date of Commencement | – | 27th November, 2013 |
Date of Completion | – | November, 2016 (Extended upto Nov, 2017) |
Up to Date progress (As on Oct., 2017) | – | 43.00% |
Sewerage & Sanitation Sub-Project:
Sewerage & Sanitation Sub-Project hnuaiahhianheng contract hnate hi implement mek a ni:-
- Construction of 10 Community Toilet Blocks
Bethlehem Vengthlang, Bawngkawn Market, Zarkawtleh Mission Vengte, AMC (Thuampui Veng), College Veng, Kulikawn (Ngaizel) New Market, Zemabawk Bazar lehDawrpuiVengte an ni. Zawhfeltawhleh a enkawltutehnenahlanfelvekannitawh.
Contractor | – | M/s Gangwal Engineering and Construction Ltd,Silchar |
Contract Amount | – | INR 179 lakhs |
Expenditure | – | INR 178.81 lakhs |
Date of Commencement | – | 29th August, 2013 |
Date of Completion | – | August,2015, (Extended upto Oct, 2015) |
Up to Date progress (As on Oct., 2017) | – | Completed and handed over |
Approach Road and Land Development for STP
Contractor | – | M/s CLT ConstructionLtd,Kolkata |
Contract Amount | – | INR 343lakhs |
Expenditure | – | INR 343lakhs |
Date of Commencement | – | 26th February, 2013 |
Date of Completion | – | November, 2016 (Extended upto Dec., 2016) |
Up to Date progress (As on Oct., 2017) | – | 100% Completed |
Supply, Installation & Commissioning of 5 Cess Pool Cleaners
Contractor | – | M/s Gangwal Engineering and Construction Ltd,Silchar |
Contract Amount | – | INR 87.57 lakhs |
Expenditure | – | INR 87.57 lakhs |
Date of Commencement | – | 18th May, 2012 |
Date of Completion | – | October, 2013 |
Up to Date progress (As on Oct., 2017) | – | Commissioned and handed over to AMC |
Construction of Sewerage Treatment Plant
Contractor | – | M/s Eco-Protection Engineers Pvt Ltd,Chennai |
Contract Amount | – | INR 2246.27 lakhs |
Expenditure | – | INR 1652 lakhs |
Date of Commencement | – | 27th November, 2013 |
Date of Completion | – | November, 2016 (Extended uptoDecember., 2017) |
Up to Date progress (As on Oct., 2017) | – | 81.2% |
Providing, Laying, Jointing & Commissioning of Sewerage Networks (46 kms).
Contractor | – | M/s Tantia Construction Pvt Ltd., Kolkatas |
Contract Amount | – | INR 3172.92 lakhs |
Expenditure | – | INR 2169 lakhs |
Date of Commencement | – | 27th November, 2013 |
Date of Completion | – | December, 2017 |
Up to Date progress (As on Oct., 2017) | – | 59.50% Sewer line 18.19Km out of 46Km already laid and 768 Manhole constructed out of 2222 Nos. |
Procurement of Dustbins for Aizawl City
Contractor | – | M/s Nilkamal Ltd Kolkata. |
Contract Amount | – | INR 343lakhs |
Expenditure | – | INR 305lakhs |
Date of Commencement | – | 16th June, 2015 |
Date of Completion | – | April,2017 (Extended due to additional procurement) |
Up to Date progress (As on Oct., 2017) | – | 100 %Completed |
- Thawhthumna(Project-III) ah hian Aizawl khawpuitana a tui pump belhna37-MLD capacity tan te, Tuipipehluitawhthuamthatnaturatanveng/zone dang 35-ah tepipesize chi hranghrangkm 255.88 Kmphum tum ani a, Tuidahkhawlnatuizem(Reservoir) thar9Nos , Ruahtuidahkhawlnatuizem(RWH) 10-Nos,Aizawl khawpuibawlhlawhlakkhawm a sawngbawlnahmun Sanitary Landfilte, Septik tank chhuaktharenchhinnaDemonstration of Septage management throuthBio-DigesterNos i.e Household 5150 (appx)atante atelbawkani. HenghnathawhnaturhianRs776.81Croreruahmanphawta ni a, ADB/ MoUDchuan a pawmfeltawhani.Tunahhianngawrhtak a thawhchhohmekania ,Kum 2019 ah chuanzawhfelhmanturahmalakmek a ni.
- Water Supply Sub-Project:
- Tui Supply 37 MLD Capacity a AugmentationKum2018 (Program completion time) water demand hi tuna tui supply capacity hiana chawmzotawh dawn lohavangin Intermediate (2030) demand 71.22 MLD meet theiturtal a program kalpui a ngaihavangin Project-3 ah hi chuan a tir project scope ruahmanbakah, Aizawl khawpuitana37MLD Tui pump belhnahna hi a tela.
Contractor | – | M/s Eco Protection Engineers Pvt Ltd,Chennai |
Contract Amount | – | INR 15667 lakhs |
Expenditure | INR 1531 Lakhs | |
Date of Commencement | – | 30th March, 2017 |
Date of Completion | – | 42 –Months/ 30th of September 2020 |
Up to Date progress (As on Oct., 2017) | – | Work execution Just Started with approval of drawings and start of procurement of materials by the contractor. |
Contractor thlantak Eco Protection Engineers Pvt Ltd,Chennaitechuanhna an tan tawh a. Survey tezawh a nitawh a, Drawing leh Design teenfelmek a ni a, kawnglaihhna an tan tawh a tin hmanruate contractor in an la khawmmek a ni.
- Water Supply distribution networks and feeding main :
Contractor | – | M/s Vishwa-Gayatri (JV), Hyderabad |
Contract Amount | – | INR 14342.22 lakhs |
Expenditure | 2475 Lakhs | |
Date of Commencement | – | 9th May, 2016 |
Date of Completion | – | 48–Month/ 8th of May 2020 |
Up to Date progress (As on Oct., 2017) | – | 19.47 % Work execution Started only recently. 39 Km Length laid |
Pipe phum tur zawng zawng hi avaiin Km 255.88 ani a. Hetahhian Feeder main Tuizemlian a tuichhunluhnatur 33.66Km lehTuisemnatur 224.22 Km a tel a. Pipe size hi 40-400mm thleng a tel a ni a.A hna hi 24th November 2016 atanginanthawk tan tawh a ni.Khawchhunghmunengngemawzat ah hnathawhmek a ni a. Pipe lehhmanruamamawhtepoh order tawh a ni.
(iii) Zonal Tank Pakua(9): Sihphir – I (260KL), Sihphir – II (260 KL), ATC Durtlang (400 KL), RamhlunPWD Mual (260 KL), Lawipu (400 KL), Central Jail (400 KL), Tuiovamit (260 KL), Sakawrtuichhun (300 KL), Phunchawng (260 KL)
Rain Water Harvesting Tank sawm (10) : Sihphir (100 KL), Chaltlang Higher Secondary School (50 KL), Hrangchhuana High School (150 KL), Thuampui (100 KL), Bethlehem (100 KL), Bethlehem Vengthlang (100 KL), College Veng (100 KL), Tlangnuam (100 KL), Melthum (100 KL), Rangvamual (100 KL).
Contractor | – | M/s S.S. Construction Chaltlang |
Contract Amount | – | INR 1200.55 lakhs |
Expenditure | INR 533.00 lakhs | |
Date of Commencement | – | 9thMay, 2016 |
Tentative Date of Completion | – | 8thNovember, 2018 |
Up to Date progress (As on Oct., 2017) | – | 59.21 % |
SCADA management System: Pumping System tharte, Tuisemdarhnalehtuidahkhawlzatte, Pipeline pressure zatte, Current hmandante, mumal taka hriatzungzunganihtheihnaturin control room pakhatatangin computer nen a thlunzawmtir tum ani. Tender chhuahtur a hmalakmek a ni.
- Sanitation/Septage Management Sub-Project:
- Construction of Bio-Digester
Defence technology-Bio-digester hi Septic Tank tha chi, khatvetheiloleh Soak Pit hranpasiamngailo a ni a, tuiril/effluentlo luangchhuak hi a rimchheve lo a,kawr a luantirmaitheihkhawp a him a ni. BioDigesterstehi chhungkaw 10, 20, 30 leh 50tetanahmantursiammek a nia.Hei hi technology innovationatanMoUD, GoI in a ruahmantel a ni. Hengbakahhian awareness and documentation tepawh a telbawk a ni.
Bio-Digester hna hi Contractor thlantak M/s Superflow Engineering Corporation Pvt. Ltd. Gwalior tehianchaktakinhmaan la mek a,zone paruk a site 55 ah Bio- Digester hi siammek a ni.
Contractor | – | M/s Superflow Engineering Corporation Pvt. Ltd. Gwalior |
Contract Amount | – | INR 1308 lakhs |
Expenditure | INR 64 lakhs | |
Date of Commencement | – | 5thApril, 2017 |
Tentative Date of Completion | – | 30 Months/ 5thOctober, 2019 |
Up to Date progress (As on Apr. 18) | – | 22.86 % |
(ii)Packaged Aerate Wastewater Treatment Plant – Johkasou
Packaged Aerate Wastewater Treatment Plant – Johkasou hiJapan technology hmangami 30, 100leh 500 tethlisawngbawlnaatan a hmantheihturabuatsaih tum a ni.Hei hi Tender chhuah a la ni lo.
(iii) Single Window System
Tin, awlsam taka septage management kalpuianihtheihnaturin Single Window System hi AMC tenenatangkawp in mipui tan a chhawpchhuah tum anibawk.
Hei hi Tender chhuah a la ni lo.
- Municipal Solid Waste Resource Management System Sub Project:
- Construction of Sanitary Landfil& Compost Plant
Solid Waste Resource Management hnuaiahhianTuirialahBawlhhlawhsawngbawlnahmuntur SanitaryLandfilbuatsaihmekania a hetahhianhnathawhtur item techu:
- 2 units of 11 TPD capacity Vermi-Compost Plant (wet waste) eachbawlhlawhtawihtheiatangachangpatleithasiamnatur.
- 2 units of 37 TPD capacity resource management centre (dry waste)bawlhlawhtawitheiloatangahralhchhuahtheihturtangkaithliarhrannahmun.
- 1 unit of 50 TPD mechanical composting planteachbawlhlawhtawihtheiatangakhawlhmangaleithasiamnatur.
- Closure of existing dumping site,kanbawlhlawhpaihnahmanlaimektihtawp.
Contractor | – | M/s V. Lalbiakzama, Venghlui |
Contract Amount | – | INR 3058 lakhs |
Expenditure | INR 911 lakhs | |
Date of Commencement | – | 18thAugust, 2016 |
Date of Completion | – | 30 months/17th Feb 2019 |
Up to Date progress (As on Oct., 2016) | – | 12.52 % Completed Work in full swing |
(ii) Procurement of 54 nos of Garbage Vehicles
Bawlhlawhpaihna Motor (Garbage Vehicle) 54 Noslei a ni a, AMC tehmanturinhlanfel a nitawhbawk.
Contractor | – | M/s ZothanAutoworks-TPS Infra JV Aizawl |
Contract Amount | – | INR 985 lakhs |
Expenditure | INR 1070lakhs | |
Date of Commencement | – | 31st Jan, 2017 |
Date of Completion | – | 18 months/31st July 2018 |
Up to Date progress (As on Oct., 2016) | – | 100% Completed and handed over to user AMC |
(iii) Procurement of Wheel Barrow by Shopping
KhawlaibawlhlawhphiahfainaatanabawlhlawhphurhnaturWheel Barrowpawh lei tawhani.
Amount INR 14.00 Lakhs
(iv) Procurement of Protection material by Shopping
Bawlhlawhsawngbawltutehriselnangaihtuahin an hmanturkawr, Boot,Glove etc., (Personal protection equipments) teleifeltawhani.
Amount INR 10.00 Lakhs